Facility Master Plan Series 1

Budget

$221,390,000

Spent

—

Missing data: spending figures are coming from DPSCD

Paid for by

Facility Master Plan

Runs through 2030–31

Projects

17

Where projects stand

  • 3 Not started
  • 3 Design
  • 4 Construction
  • 1 Demolition
  • 3 Closeout
  • 3 Other

17 projects

Phase
Completion date
Open
Building Demolition
Not started
Target: Spring 2029
New Building
Design
Target: August 2028
City Airport Renovations
Construction
Target: August 2026
Relocation to City Airport
Other
Target: Summer 2026
CTE Space Renovations
Construction
Target: Summer 2026
CTE Program Relocation
Design
Target: Summer 2026
Culinary Program Relocation
Other
Target: Fall 2028
Building Demolition
Demolition
Target: Spring 2027
Relocation to Swing Space
Closeout
Completed (date to be confirmed)
Building Demolition
Closeout
Completed (date to be confirmed)
New Building
Construction
Target: August 2027
Athletic Field
Not started
Target: Fall 2029
New Building
Construction
Target: August 2027
Building Demolition
Design
Target: Spring 2028
New CTE Annex
Closeout
Completed (date to be confirmed)
Demolition
Not started
Target: Winter 2027
Phase Out & Demolition (Series 1)
Other
Target: Summer 2029