Facility Master Plan Series 2

Budget

$13,372,708

Spent

—

Missing data: spending figures are coming from DPSCD

Paid for by

Facility Master Plan

Runs through 2030–31

Projects

13

Where projects stand

  • 13 Closeout

13 projects

Phase
Completion date
Open
Relocation to Detroit Lions Academy
Closeout
Completed (expected Summer 2024)
New Alternative Campus
Closeout
Completed (expected Summer 2023)
Relocation to Alt. Campus
Closeout
Completed (expected Summer 2023)
Relocation to Northern
Closeout
Completed (expected Summer 2023)
PRMX Swing Space Renovation
Closeout
Completed (expected Summer 2024)
Swing Space
Closeout
Completed (expected Summer 2023)
Relocation to Alt. Campus
Closeout
Completed (expected Summer 2023)
Reactivation & Renovations
Closeout
Completed (expected Summer 2024)
Print Shop Relocation
Closeout
Completed (expected Summer 2024)
Parking Lot
Closeout
Completed (expected Summer 2024)
Relocation to Northern
Closeout
Completed (expected Summer 2023)
Relocation to Alt. Campus
Closeout
Completed (expected Summer 2023)
Support Staff Relocation
Closeout
Completed (expected Summer 2023)