Facility Master Plan Series 6

Budget

$126,173,373

Spent

—

Missing data: spending figures are coming from DPSCD

Paid for by

Facility Master Plan

Runs through 2030–31

Projects

199

Where projects stand

  • 51 Planning
  • 118 Procurement
  • 27 Design
  • 2 Closeout
  • 1 Other

199 projects

Phase
Completion date
Open
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Closeout
Completed (expected Fall 2026)
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Design
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Planning
Target: Fall 2029
LED Lighting
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Planning
Target: Fall 2029
LED Lighting
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing (annex)
Design
Target: Fall 2029
Exterior Doors and Windows (annex)
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating (annex)
Procurement
Target: Fall 2029
Exterior Doors and Windows (annex)
Procurement
Target: Fall 2029
Roofing (annex)
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing (annex)
Design
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows (annex)
Procurement
Target: Fall 2029
Roofing (annex)
Design
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Exterior Doors and Windows
Other
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Exterior Surfaces
Planning
Target: Fall 2029
Interior
Planning
Target: Fall 2029
Systems
Planning
Target: Fall 2029
Track
Planning
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Plumbing
Procurement
Target: Fall 2029
Roofing
Closeout
Completed (expected Fall 2026)
Exterior Doors and Windows
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing (annex)
Planning
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Structure
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
ADA and Access
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
LED Lighting
Procurement
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Roofing (annex)
Design
Target: Fall 2029
Exterior Doors and Windows (annex)
Procurement
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
ADA and Access
Procurement
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Cooling
Planning
Target: Fall 2029
Exterior Doors and Windows
Planning
Target: Fall 2029
Roofing
Planning
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Roofing
Design
Target: Fall 2029
Heating
Procurement
Target: Fall 2029
Cooling
Procurement
Target: Fall 2029
Exterior Doors and Windows
Procurement
Target: Fall 2029
Interior
Planning
Target: Fall 2029
Plumbing
Planning
Target: Fall 2029
Heating
Planning
Target: Fall 2029
LED Lighting
Planning
Target: Fall 2029