Where things stand
ConstructionStep 5 of 6
The work
Elevator Replacement
A plain-language description is coming from DPSCD.
Dates
- Start
- Spring 2024
- Target completion
- Fall 2026
Other work at this school or site
- RoofingCompleted (expected Fall 2026)Closeout
- Mechanical System UpgradesConstruction
- Electrical Power UpgradesConstruction
- PK Expansion (New Classroom(s))Completed (expected Fall 2022)Closeout
- Elevator ModernizationProcurement
Money
- Budget
- Missing data
- Spent
- Missing data
- Paid for by
- Board-Approved Capital Funds